In Chitunda gaat de bouw door

Project update van 29 september 2023 door Mussa Nyirenda


Mussa (projectcoördinator) is in Chitunda en vertelt over de voortgang van de bouw...

"The chitunda project took place in July and the participants and community members worked so hard to have the project completed in good time. By the time the handing over of the school was being done most of the works had been completed such as bricklaying, ring beam, roofing and part of plastering. Currently the community has completed work on plastering, skirting and they are now working on the floor. The remaining works so far is finishing with flooring, pointing, drainage, painting, fixing doors and glasses. The community is committed to completing all the works so that within this year the classrooms should be ready to be used by the learners."