Het hoogste punt is bereikt

Project update van 6 juli 2021 door Mussa Nyirenda


Een verslag van projectcoördinator Mussa over de voortgang van het project in Endhlaleni

"A lot of progress has been made at Endhlaleni on the school block as they have already reached the highest point. The bricklaying work on the walls is almost complete on all the sides. Currently the trusses have been mounted and have already been put on the roof. The remaining work now is beam filling and putting on the iron sheets and thereafter plastering, flooring, drainage, pointing and painting. The work is progressing well despite that the absence of the groups is heavily felt. The fun and excitement accompanied by the team work when the group is around is not there."