Monitoring Report - Project BO118

Project update van 14 november 2018


The participation of the community is very active, being part of the search and hiring of new workers, purchase of material and supervision of the work.

Currently the construction is in phase 2 of brick walls adobito, we must highlight that the progress made by the group of volunteers to be the first time we work with people with different abilities was challenging and the progress was not as expected. This has made us have challenges when finding a contractor that fits our budget, we have chosen to hire staff for days and the advance was not the best having to finish this mode of work, two weeks ago we talked with a new contractor who have the best price to finish this construction and will start in the coming days. The time that he will use for the finalization is 10 weeks, we plan to deliver it to the community at the end of January 2019.