De bouw in Chamkoko gaat door

Project update van 12 november 2021 door Mussa Nyirenda


Projectcoördinator Mussa was in Chamkoko vorige week en doet verslag van de bouw.

"The construction of the two teachers houses, toilet and Girls Changing room is progressing well despite the delays due to community participation which has not been at its best. One teachers house is currently almost complete while the other one is still under construction. Painting and fixing of glasses is yet to be done. The progress has been slow but there is hope that by 20th November the teachers houses will be completed. The community is already working on the kitchen for teachers houses and renovation of teachers house. There are already more teachers at the school but the challenge has always been teachers accommodation. The big support in terms of teachers accommodation will obviously ease the challenge at the school."